We’ve just uploaded some exciting new photos from the Skainos site showing the progress from some unusual view, including the top of the tallest crane on site.
You can view these photos from the Skainos gallery on flickr (see the link in the sidebar) or on the Skainos facebook page, again, the link is in the sidebar.
All construction work is due to cease for a week from Friday 8 July until Monday 18th as the traditional builders holidays begin. Farrans however are only shutting down for a week and will be back in full swing on 18th. In the next six weeks we expect to see all the steelwork erected on the West side of the development and also the top floor slab in blocks A and B as well as the delivery of the pre-fabricated apartment units to top out those blocks.